PETROLINE: 5 PIPE WELDERS FOR A 9-DAY PLANT SHUTDOWN
Plant & Pipeline Construction

PETROLINE: 5 PIPE WELDERS FOR A 9-DAY PLANT SHUTDOWN

Additional TIG expertise for stainless and carbon steel piping within a narrow shutdown window

Overview

Industry
Plant and pipeline construction
Region
North Rhine-Westphalia
Challenge
Welding work on pressure piping under AD 2000 / DIN EN ISO 9606 requirements
Services
TIG (141)STICK WELDING (111)PIPELINE FABRICATION
At a glance
5 experienced pipe welders available within 96 hours
54 welded joints completed during the shutdown window
Work delivered to AD 2000 requirements
The challenge

The challenge

Initial situation: Several pipe packages had to be renewed within an extremely tight shutdown window.

Bottleneck: The client’s own workforce was not sufficient to cover all trades in parallel.

Quality requirement: Mixed materials, clean welding documentation and reliable acceptance were mandatory.

Project risk: Every lost day would have triggered shutdown costs and schedule slippage.

Our approach

Detailed intake: Isometrics, materials, weld counts and priorities were aligned package by package before the start.

Targeted qualification match: Only pipe welders with relevant shutdown experience and mixed-material capability were deployed.

Progress-based deployment concept: The team was prioritised around the most critical piping sections and handover milestones.

Documentation & steering: Weld logs, records and daily coordination with site management and QA were centralised through one point of contact.

Our approach

Measured results

5
SPECIALISTS DEPLOYED
96H
LEAD TIME TO START
54
WELDED JOINTS COMPLETED
0 DAYS
SHUTDOWN OVERRUN

Petroline achieved the planned restart without any schedule loss. The decisive factor was the combination of fast staffing and disciplined documentation control.

Measured results

Are you facing a similar challenge?

More case studies